This Annex provides
a consolidation of the mitigation measures recommended for the Project. The Implementation Schedule has the
following column headings:
EIA
Ref
This denotes the section number or reference from the EIA
Report Main text.
EM&A Log Ref
This denotes the sequential number of each of the
recommended mitigation measures specified in the Implementation Schedule.
Environmental
Protection Measures
This denotes the recommended mitigation measures, courses of
action or subsequent deliverables that are to be adopted, undertaken or
delivered to avoid, minimise or ameliorate predicted environmental impacts.
Objectives
This denotes the objectives of the recommended mitigation
measures and main concerns to address.
Location/Duration
of Measures/Timing of Completion of Measures
This indicates the spatial area in which the recommended
mitigation measures are to be implemented together with details of the
programming or timing of their implementation.
This denotes where the responsibility lies for the
implementation of the recommended mitigation measures.
This denotes the stage at which the recommended mitigation
measures are to be implemented either during the Design, Construction,
Operation or Decommissioning.
Relevant
Legislation
This section defines the controlling legislation that is
required to be compiled with.
EIA* Ref. |
EM&A Log Ref |
Environmental Protection Measures |
Objectives |
Location/Duration of Measures/Timing of Completion of Measures |
Implementation Agent |
Implementation Stage** |
Relevant Legislation & Guidelines |
|||
|
|
|
|
|
|
Des |
C |
O |
Dec |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WATER
QUALITY |
|
|
|
|
|
|
|
|
Section 2.4 of Part 3 |
1 |
Although there is no requirement for constraints on timing
or sequencing apparent from the assessment, as all scenarios have been
demonstrated to be acceptable with the required mitigation measures in
place. The following operational
constraints shall be implemented to ensure no unacceptable water quality
impacts. |
|
|
|
|
|
|
|
|
Section 2.4 of Part 3 |
|
·
Dredging
operations within the East of Sha Chau Facility do not exceed 100,000 m3
week-1. |
To avoid unacceptable water
quality impacts during dredging |
At the East of Sha Chau work
site, throughout the whole duration of the construction period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
Backfilling operations within the East
of Sha Chau Facility do not exceed a disposal rate of 26,700 m3
day-1. |
To avoid unacceptable water
quality impacts during backfilling |
At the East of Sha Chau work
site, throughout the whole duration of backfilling |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
Capping operations within the East of
Sha Chau Facility do not exceed a disposal rate of 26,700 m3 day-1. |
To avoid unacceptable water
quality impacts during capping |
At the East of Sha Chau
Facility work site, throughout the whole duration of capping |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
No overflow is permitted from the
trailer suction hopper dredger but the Lean Mixture Overboard (LMOB) system
will be in operation at the beginning and end of the dredging cycle when the
drag head is being lowered and raised.
|
To avoid unacceptable water
quality impacts during dredging |
At the East of Sha Chau work
site, throughout the whole duration of the construction period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
Dredged marine mud shall be disposed of
in a gazetted marine disposal area in accordance with the Dumping at Sea Ordinance (DASO) permit conditions. |
To avoid unacceptable water
quality impacts during dredging |
At the East of Sha Chau work
site, throughout the whole duration of the construction period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
2 |
The following good practice measures
shall apply at all times: ·
All disposal vessels should be fitted
with tight bottom seals in order to prevent leakage of material during
transport. |
To prevent leakage of
material during transport |
At the East of Sha Chau work
site, throughout the whole duration of the disposal period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
All barges should be filled to a level,
which ensures that material does not spill over during transport to the
disposal site and that adequate freeboard is maintained to ensure that the
decks are not washed by wave action. |
To ensure that material does
not spill over during transport and the decks are not washed by wave action |
At the East of Sha Chau work
site, throughout the whole duration of the construction and operation period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
After dredging, any excess materials
should be cleaned from decks and exposed fittings before the vessel is moved
from the dredging area. |
To avoid potential adverse
water quality impacts associated with dredging |
At the East of Sha Chau
dredging sites, throughout the dredging period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
The contractor(s) should ensure that
the works cause no visible foam, oil, grease, litter or other objectionable
matter to be present in the water within and adjacent to the dredging site. |
To avoid potential adverse
water quality impacts associated with dredging |
At the East of Sha Chau
dredging sites, throughout the dredging period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
If installed, degassing systems should
be used to avoid irregular cavitation within the pump. |
To avoid adverse water
quality impacts due to irregular cavitation within the pump |
At the East of Sha Chau work
site, throughout the whole duration of the construction and operation period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
Monitoring and automation systems
should be used to improve the crew’s information regarding the various
dredging parameters to improve dredging accuracy and efficiency. |
To improve dredging accuracy and
efficiency |
At the East of Sha Chau
dredging site, throughout the dredging period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
Control and monitoring systems should
be used to alert the crew to leaks or any other potential risks. |
To alert the crew to leaks
or any other potential risks |
At the East of Sha Chau work
site, throughout the whole duration of the construction and operation period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
When the dredged material has been
unloaded at the disposal areas, any material that has accumulated on the deck
or other exposed parts of the vessel should be removed and placed in the hold
or a hopper. Under no
circumstances should decks be washed clean in a way that permits material to
be released overboard. |
To prevent release of dredged materials
overboard |
At the East of Sha Chau
dredging sites, throughout the dredging period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 2.4 of Part 3 |
|
·
All dredgers should maintain adequate
clearance between vessels and the seabed at all states of the tide and reduce
operations speed to ensure that excessive turbidity is not generated by
turbulence from vessel movement or propeller wash. |
To ensure that under-vessel
turbidity is not generated by turbulence from vessel movement or propeller
wash |
At the East of Sha Chau
dredging sites, throughout the dredging period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 3 of |
3 |
Water quality
monitoring will be required for the following activities at the East of Sha
Chau Facility: ·
Dredging of each pit; ·
Backfilling of each pit with
contaminated mud; and ·
Capping of each pit with uncontaminated
Mud. |
To avoid impacts to water
quality during dredging, backfilling and capping |
At the East of Sha Chau work
sites, throughout the dredging, backfilling and capping period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
Section 3 of |
4 |
Sediment
quality monitoring will be required for the backfilling activities at the
East of Sha Chau Facility. |
To avoid impacts to water
quality during backfilling |
At the East of Sha Chau work
sites, throughout the backfilling period |
Contractor |
|
|
|
|
Water
Pollution Control Ordinance |
|
|
MARINE ECOLOGY |
|
|
|
|
|
|
|
|
Section 3 of |
5 |
In accordance with the guidelines in
the EIAO-TM, the general policy for
mitigating impacts to marine ecological resources shall be applied in order
of the following priority:
·
Avoidance: Potential impacts should be avoided
to the maximum extent practicable by adopting suitable alternatives; ·
Minimisation: Unavoidable impacts should be
minimised by taking appropriate and practicable measures such as constraints
on the intensity of works operations (eg dredging rates) or timing of works
operations; and ·
Compensation: The loss of important species and
habitats may be provided for elsewhere as compensation. Enhancement and other conservation
measures should always be considered whenever possible. |
To avoid potential impacts
to marine ecology |
During project planning and
design |
Design Team |
|
|
|
|
EIAO-TM |
Section 3 of |
6 |
Sediment toxicity monitoring will be
conducted to assess the potential toxicity impacts to marine life due to
disposal activities. |
To avoid impacts to marine
life due to disposal activities |
At the East of Sha Chau
Facility, throughout the backfilling period |
Contractor |
|
|
|
|
|
|
7 |
Benthic recolonisation monitoring will
be required to assess the recolonisation status of benthic fauna on capped
pits. |
To assess the recolonisation
status of benthic fauna on capped pits |
At the East of Sha Chau
Facility, after capping of mud pits |
Contractor |
|
|
|
|
|
|
|
Hazard to
Health |
|
|
|
|
|
|
|
|
Section 3 of |
8 |
A risk assessment to verify
that no unacceptable risk are occurring to either human health or marine
mammals as a result of consuming prey species from the waters in the vicinity
of the pits will be required. |
To assess hazard to health
of humans and marine mammals |
In the vicinity of the East
of Sha Chau Facility, throughout the disposal period |
Contractor |
|
|
|
|
|
|
|
CULTURAL HERITAGE |
|
|
|
|
|
|
|
|
Section 7 of Part 2 |
9 |
A watching brief by a
qualified archaeologist to be conducted during dredging in the areas of
identified anomalies in the South Brothers pit B, in the event that the South
Brothers Pits are needed. |
To establish the
archaeological potential of the anomalies. |
At the South Brothers
Facility if it is to be used, during the construction works |
Contractor |
ü |
|
|
|
AMO
Marine Archaeological Investigation Guidelines |